... .... .... and ventilate and dry and heat .... and ventilate and dry .... .... and heat ....
Friday, October 29, 2010
Cimbali Bistro Espresso
floor drying program
... .... .... and ventilate and dry and heat .... and ventilate and dry .... .... and heat ....
... .... .... and ventilate and dry and heat .... and ventilate and dry .... .... and heat ....
Monday, October 25, 2010
Flat White Discoloration On Nose
screed
.... on Friday, 22.10. The screed was introduced, the result is far from perfect!
On Thursday, we start with the floor dry LWZ program - in addition we are second from the (You can borrow in the DIY / Building Materials) use week then still a dehumidifier.
is important that the surface is sweating right in the first 5 days, not air and not heat well. After that, get out the moisture from the house, so airing several times a day, the screed drying cycle and the air dryer worried then the rest
So it is waiting to scrap again ...
.... on Friday, 22.10. The screed was introduced, the result is far from perfect!
On Thursday, we start with the floor dry LWZ program - in addition we are second from the (You can borrow in the DIY / Building Materials) use week then still a dehumidifier.
is important that the surface is sweating right in the first 5 days, not air and not heat well. After that, get out the moisture from the house, so airing several times a day, the screed drying cycle and the air dryer worried then the rest
So it is waiting to scrap again ...
| |
| how it glitters ... |
Friday, October 22, 2010
Show Breasts With Kiss
house position 3 Weeks
has now installed the LWZ finished the remaining Lüftungs-/Heizungs-/Wasser-Rohre laid out by the pressure test and everything put into operation.
The floor cutouts for the giant-160x90 Bette shower tray, we also set the same, thanks to Michael, the friendly neighbor - who has also still the same help with beer supplies! ;-)
We incidentally mount only Bettefloor (OG) or Bette Super Flat (EC) mounting frames - unfortunately these are not yet delivered, the mounting frame (including recess means) can namely already assembled on the floor to stay inside, and - aba Wurscht - will work that way too. The screed can
So come on Friday ...
with the installation team, we have been absolutely great satisfaction - All great to get guys who always work hard late into the night to finish all construction sites. Thanks man! :-)
has now installed the LWZ finished the remaining Lüftungs-/Heizungs-/Wasser-Rohre laid out by the pressure test and everything put into operation.
The floor cutouts for the giant-160x90 Bette shower tray, we also set the same, thanks to Michael, the friendly neighbor - who has also still the same help with beer supplies! ;-)
We incidentally mount only Bettefloor (OG) or Bette Super Flat (EC) mounting frames - unfortunately these are not yet delivered, the mounting frame (including recess means) can namely already assembled on the floor to stay inside, and - aba Wurscht - will work that way too. The screed can
So come on Friday ...
with the installation team, we have been absolutely great satisfaction - All great to get guys who always work hard late into the night to finish all construction sites. Thanks man! :-)
| |
| the Monschder * harhar * |
| |
| snakes living room |
| |
| kitchen snakes |
| |
| recess small shower |
| |
| recess shower |
| |
| spa shower with light window * harhar * |
| |
| Office snakes (including screed floor box for LAN / phone / electricity) |
| |
| Badschlangen (before opening) |
Tuesday, October 19, 2010
Name For Clutural Fest.
Body shop party
I know I know ....... it's gone again weeks since my last post ... running out of time .. and at the end of the week think it was but it was Monday .... oh dear
Well so far so good. So we held on 11/09/2010 after breaking a small shell of the roof party. We invited our families, friends, work colleagues, old and new neighbors. The weather has really meant that day very well with us, the sun was shining from the sky and there are very many people came. On the whole it was a very nice and successful day.
We had the opportunity to meet some of our new neighbors and it was just great. Very nice and open people.
Very pleased I was also visiting my Great Aunt Helen. Oh, and my Dani was also there with my little mini friend Lina and Olli.
Jochen's dad gave us all with delicious sausages and steaks supplies and especially I would also like to thank you again Rebecca for their active support. Without it, some guests had been sitting on "dry land". So again to awful love you for that.
The kids are not left short and huge fun had our dug especially for the connections of the air-water heat pump pit with a lot of zeal fill them again * laughing *..... So the huge mound of earth behind the house was the No. 1 attraction, accordingly, the mudlarks saw then too.
So, my friends, I wanted to just quickly now to prepare the images of the body shop party. But I promise the next post can not be long in coming ...... it is in fact much has happened - particularly, the OWN WORK started * laughs *..... but this next time around.
Until then, all love
Ivonne
I know I know ....... it's gone again weeks since my last post ... running out of time .. and at the end of the week think it was but it was Monday .... oh dear
Well so far so good. So we held on 11/09/2010 after breaking a small shell of the roof party. We invited our families, friends, work colleagues, old and new neighbors. The weather has really meant that day very well with us, the sun was shining from the sky and there are very many people came. On the whole it was a very nice and successful day.
We had the opportunity to meet some of our new neighbors and it was just great. Very nice and open people.
Very pleased I was also visiting my Great Aunt Helen. Oh, and my Dani was also there with my little mini friend Lina and Olli.
Jochen's dad gave us all with delicious sausages and steaks supplies and especially I would also like to thank you again Rebecca for their active support. Without it, some guests had been sitting on "dry land". So again to awful love you for that.
The kids are not left short and huge fun had our dug especially for the connections of the air-water heat pump pit with a lot of zeal fill them again * laughing *..... So the huge mound of earth behind the house was the No. 1 attraction, accordingly, the mudlarks saw then too.
So, my friends, I wanted to just quickly now to prepare the images of the body shop party. But I promise the next post can not be long in coming ...... it is in fact much has happened - particularly, the OWN WORK started * laughs *..... but this next time around.
Until then, all love
Ivonne
Friday, October 15, 2010
Gundam Dynames Blueprint
House position 2 Weeks
Today, the heating technicians arrived. They have also started the same Stiebel Eltron SOL LWZ build 303 to solder the heating pipes, to install the water pipes and ventilation ducts, and the floor structure (insulation, etc.) to be interpreted. Prima. :-)
Today, the heating technicians arrived. They have also started the same Stiebel Eltron SOL LWZ build 303 to solder the heating pipes, to install the water pipes and ventilation ducts, and the floor structure (insulation, etc.) to be interpreted. Prima. :-)
Wednesday, October 13, 2010
Frequency For Hindi Channelin Bahrain
House connection
Meanwhile, we also have the service entrance through the multi-branch case, ie, water, electricity, T-Com - but the action was real injury ne ... I have to be small at first gather again .... no no not because I dug the ditch, but because the enbw just such a complicated and saublöder heap, which provides on any other planet!
Meanwhile, we also have the service entrance through the multi-branch case, ie, water, electricity, T-Com - but the action was real injury ne ... I have to be small at first gather again .... no no not because I dug the ditch, but because the enbw just such a complicated and saublöder heap, which provides on any other planet!
| |
| the Mariana Trench - 2500 km long, 11km deep |
| |
| electricity, water, T-Com |
| |
| the multi-branch sleeve |
| |
| jo |
| |
| MSH main floor execution |
| |
| branching |
| |
| eingesandet, filled, compacted |
Tuesday, October 12, 2010
Unevenly Waxed Eyebrows
house position 3-5. Days
on 3 .... to 5 Days the roof was covered fully, with the interior work began, the insulation is introduced, sheetrock installed, gutters fixed, aligned windows and walls again, etc. ..
The electricians were two of ham on the spot and also the same at full throttle, all the lines drawn up on a floor box, all cans and distribution set, the fuse box installed, current test is run, etc. .. and now it s already finished! Great guys! Thanks again! :-)
Again, it really needs to mention that all the works were carried out Absoulute top - so far there is absolutely nothing at all open to criticism (and we are really PINGEL!) and rumgehüpft actually the whole time the guys here ... by the way great opportunity to make one or the other thing like itself, such as schonmal mount, recessed, or speaker cable into the ceiling before they are then closed with plaster, or the satellite facility on the roof while the scaffolding is still ... etc ... druff
on 3 .... to 5 Days the roof was covered fully, with the interior work began, the insulation is introduced, sheetrock installed, gutters fixed, aligned windows and walls again, etc. ..
The electricians were two of ham on the spot and also the same at full throttle, all the lines drawn up on a floor box, all cans and distribution set, the fuse box installed, current test is run, etc. .. and now it s already finished! Great guys! Thanks again! :-)
Again, it really needs to mention that all the works were carried out Absoulute top - so far there is absolutely nothing at all open to criticism (and we are really PINGEL!) and rumgehüpft actually the whole time the guys here ... by the way great opportunity to make one or the other thing like itself, such as schonmal mount, recessed, or speaker cable into the ceiling before they are then closed with plaster, or the satellite facility on the roof while the scaffolding is still ... etc ... druff
| |
| roof |
| |
| interior started |
| |
| stairs in it, Plasterboard wiring tuned |
| |
| ... |
| |
| insulation |
| lay lines |
| |
| fuses installed |
| |
| s'wichtigschte I have stored in the middle (für'n closing time, eh?) |
| |
| insulation |
Subscribe to:
Posts (Atom)